§2248. Provisions for withholding payment; effect on liability of contractor or agency;
punch list; liquidated damages
A. No contracts for the construction, alteration, or repair of any public works
executed in conformity with this Part shall provide that the state or any of its agencies,
boards, or subdivisions or any other public entity letting such a contract may withhold
payment of more than ten percent of the contract price on projects of less than five hundred
thousand dollars, and five percent of the contract price on projects of five hundred thousand
dollars or more until the expiration of forty-five days after the recordation of formal
acceptance of such work, or notice of default by the contractor or subcontractor. Such
provision for withholding of payment shall in no way change or affect the liability of the
letting agency or of the contractor, subcontractor, or their sureties.
B.(1) All public works contracts shall contain a clause stating that any punch list
generated during a construction project shall include the cost estimates for the particular
items of work the design professional has developed based on the mobilization, labor,
material, and equipment costs of correcting each punch list item. The design professional
shall retain his working papers used to determine the punch list items cost estimates should
the matter be disputed later. The contracting agency shall not withhold from payment more
than the value of the punch list. Punch list items completed shall be paid upon the expiration
of the forty-five day lien period.
(2) If the public entity occupies or uses the public works, the following shall apply:
(a) The punch list shall be furnished to the contractor within ten days of substantial
completion, as defined in R.S. 38:2241.1.
(b) Within fourteen days of providing the punch list to the contractor, the punch list
may be amended by the design professional or the public entity.
(3) The provisions of this Section shall not be subject to waiver, nor shall these
provisions apply to the Department of Transportation and Development.
C. Notwithstanding any provision of law to the contrary, a public entity letting a
public works construction contract for a flood protection project or for an integrated coastal
protection project as defined in R.S. 49:214.2, as per the terms of the contract, may withhold
liquidated damages from any payments or monies otherwise due to the contractor, taking into
consideration all granted time extensions, after the expiration of the forty-five day period set
forth in R.S. 38:2242(B).
Added by Acts 1954, No. 583, §1. Amended by Acts 1978, No. 470, §1; Acts 1979,
No. 751, §1; Acts 1986, No. 194, §1, eff. June 28, 1986; Acts 2001, No. 1216, §1, eff. July
2, 2001; Acts 2020, No. 92, §1; Acts 2022, No. 756, §1.